How to make a BOQ for an interior project

The short answer

An interior BOQ lists every item you will deliver, grouped by room or trade, with a clear description, the material and finish, a unit, a quantity, a rate and an amount. Build it from measured drawings, price it from a rate library rather than memory, and list what is excluded so the scope cannot drift.

What goes on every BOQ line

What goes on every BOQ line
ColumnWhat to writeExample
ItemWhat it is and whereMaster bedroom wardrobe, 4 door
SpecificationMaterial, finish, hardware, brand18 mm BWP ply, PU finish, soft-close hinges
UnitHow it is measuredsq ft of shutter area
QuantityFrom measured drawings, not the brochure64
RateYour client rate for one unit₹2,900
AmountQuantity × rate₹1,85,600

Figures are illustrative.

Step by step

  1. Start from the brief and the measurements. Use the recce and the floor plan for sizes. A BOQ built on guessed sizes is wrong before it is priced.
  2. Choose how to group it. By room is easiest for clients to read. By trade (carpentry, false ceiling, electrical, painting) is easiest for buying and vendor work. Many firms show the client rooms and keep trades for themselves.
  3. Use the right unit for each trade. Common choices: sq ft for false ceiling, painting, flooring and shutters; running feet for skirting, cornices and countertops; numbers for fixtures and points; lump sum only when the scope truly cannot be measured.
  4. Price from a rate library. Keep one rate card with recipes for common items (a wardrobe with its carcass, shutters and hardware). Re-typing rates from an old quote is how errors and old prices creep in.
  5. Add the commercial lines. Design fee, project management fee if any, and GST. State whether rates include GST.
  6. Write the assumptions and exclusions. Civil changes, appliances, loose furniture, electrical load upgrades and society charges are common exclusions. Writing them down prevents the variation argument later.
  7. Check the margin before it goes. Compare client rate to cost rate line by line. A low-margin line is easier to fix before the client sees it.

Mistakes that cost margin

  • Lump-sum lines that hide quantities, so a change cannot be priced fairly.
  • Specifications that say "as per design", which lets the cheaper option win on site.
  • No exclusions list, so every extra becomes a free favour.
  • Quantities that never get re-measured, so the final bill does not match the work.
  • Several versions in a chat with no clear record of which one the client accepted.

Questions people ask

What is the difference between a BOQ and a quotation?

The BOQ is the itemised list of quantities and rates. The quotation is the document the client receives, which usually contains the BOQ plus the payment plan, fees, taxes, terms and exclusions.

Should an interior BOQ be by room or by trade?

Show clients a room-wise BOQ because it matches how they think. Use a trade-wise view internally for buying and vendor contracts. Good tools give you both from the same lines.

Can AI make a BOQ?

AI can draft the lines from a brief and a floor plan, which saves hours. Rates should come from your own rate library, and a person should check every line before it is sent.

How Pakka helps.

Pakka drafts BOQ lines from the client's brief and floor plan, reads room sizes from the plan, and fills every rate from your own library. The AI never writes a price: lines without a rate are flagged for you. Low-margin quotes are flagged for approval, and the won BOQ becomes the project budget and site phases.

Give us your messiest project. The first one is free.

Ten founding firms get their first project on Pakka free, set up with them over WhatsApp in an afternoon. Everyone else joins the waitlist, and we open in batches.

10 of 10 founding spots left

How the founding programme works · Questions? WhatsApp us