Interior design payment schedule: how to set client milestones

The short answer

Tie each client instalment to an event both sides can see, not to a date or a feeling that work is nearly done. A common pattern is a booking amount, a payment at design sign-off, the largest share when production or material orders start, a stage on site progress, and a final payment at handover.

A common milestone pattern

A common milestone pattern
StageReleased byTypical share
BookingSigned proposal5 to 10%
Design sign-offClient approves the final drawings10 to 20%
Production startMaterial orders placed, factory work begins40 to 50%
Site progressA checked stage on site, such as carpentry installed15 to 25%
HandoverSnags closed and handover done5 to 10%

Shares vary by firm, project size and how much is made in a factory. Use this as a starting point, not a rule.

Why events beat dates

A date-based schedule falls apart the moment the site slips, and then every payment becomes a negotiation. An event-based schedule moves with the work: when the drawings are approved or a stage passes inspection, the instalment is simply due.

Events also settle the most common argument, whether the work is really finished. If the stage is released by a quality check with photos, completion is on record.

Keeping instalments on time

  • Put the payment plan in the quotation, so it is agreed before work starts.
  • Tell the client the moment a milestone is reached, with proof, and send the invoice the same day.
  • Record part payments and TDS against the right stage, so the balance is always clear.
  • Let the client see what they have paid and what is next, so the conversation is about progress, not money.

Questions people ask

How much advance should an interior designer take?

Many firms take a booking amount of 5 to 10 percent with the signed proposal and a larger payment before production starts, so materials are never bought on the firm's own money. The right number depends on your cash position and how much is factory-made.

Should the last payment be at handover?

Yes. Keeping a final instalment until snags are closed and handover is done gives both sides a clear finish line.

How do I handle TDS on client payments?

Record the receipt with the TDS amount so the instalment shows as fully settled, and match it to the client's TDS certificate later. Your CA can confirm the rate that applies to your contract.

How Pakka helps.

In Pakka, a won quote's payment plan becomes the client's instalment plan automatically. Stages are released by events (acceptance, design complete, phase start, QC pass, handover), receipts with TDS settle the right instalment on their own, and the client sees what they have paid on their portal.

Give us your messiest project. The first one is free.

Ten founding firms get their first project on Pakka free, set up with them over WhatsApp in an afternoon. Everyone else joins the waitlist, and we open in batches.

10 of 10 founding spots left

How the founding programme works · Questions? WhatsApp us